Railways: Midlands

Asked by Dr Kieran MullanConservativeDepartment for TransportTabled Answered 5 September 2024UIN 2548

The question

To ask the Secretary of State for Transport, what progress her Department has made on the (a) designs for and (b) delivery of the Midlands Rail Hub.

Answered by Lilian Greenwood

Following approval of an Outline Business Case, £123m was released to Network Rail in March 2024 to commence detailed design of Midlands Rail Hub’s first phase (for additional services between Birmingham, Bristol, Cardiff, and Worcester), while subsequent phases are at an earlier stage of development. Subject to future decisions about affordability and value for money, the first stage could be complete by the early 2030s.

The Chancellor set out on 29 July a range of pressures on public spending, including £2.9 billion of unfunded transport specific spending. Following this, the Secretary of State’s Written Ministerial Statement on 30 July set out that the Department is undertaking an internal review of its capital spend portfolio. This will support the development of our new long-term strategy for transport. Any decisions about the portfolio will be subject to broader discussions and fiscal decisions made at Budget and Spending Review.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim