VerbatimParliament, as it happens

Hitachi: Oldbury Power Station and Wylfa Power Station

Asked by Llinos MediPlaid CymruDepartment for Energy Security and Net ZeroTabled Answered 10 September 2024UIN 4472

The question

To ask the Secretary of State for Energy Security and Net Zero, pursuant to the Answer of 5 September 2024 to Question 3867 on Hitachi: Wylfa Power Station, if he will provide a breakdown of how much of the £160 million total was spent on the site at (a)

Answered by Michael Shanks

Great British Nuclear agreed to pay £115m for the Wylfa site and up to £45m for the Oldbury site, excluding taxes.