National Grid: Paisley and Renfrewshire North

Asked by Alison TaylorLabourDepartment for Energy Security and Net ZeroTabled Answered 19 November 2024UIN 14229

The question

To ask the Secretary of State for Energy Security and Net Zero, what steps he is taking to increase the UK's grid capacity to (a) help achieve net zero goals and (b) support (i) improved rail connectivity and (ii) advanced manufacturing in Paisley and Renfrewshire North constituency.

Answered by Michael Shanks

The electricity networks are owned by private network companies and regulated independently by Ofgem. Government is working closely with Ofgem to speed up delivery of new network infrastructure and reform the connections process to help achieve clean power by 2030 and accelerate to net zero.

Under the current distribution network price control (2023-2028), Ofgem has allowed £22.2bn for network investment. This will increase capacity, enabling connections for projects across GB, including rail and advanced manufacturing.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim