VerbatimParliament, as it happens

Lower Thames Crossing

Asked by Kevin HollinrakeConservativeDepartment for TransportTabled Answered 29 November 2024UIN 15444

The question

To ask the Secretary of State for Transport, what recent estimate her Department has made of the (a) cost of preparing and (b) length of the environmental impact assessment for the Lower Thames Crossing development consent order application.

Answered by Lilian Greenwood

Due to the level of interdependency between the large number of different elements of the Lower Thames Crossing Development Consent Order (DCO) application, it is not possible to accurately attribute costs to the production of the individual documents within it. However, the total amount spent on the planning process is £295.1million.

The Environmental Impact Assessment information submitted in 2022 as part of the Lower Thames Crossing DCO application comprised of approximately 12,000 pages.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim