Infrastructure: Planning Permission

Asked by Kevin HollinrakeConservativeMinistry of Housing, Communities and Local GovernmentTabled Answered 5 December 2024UIN 16199

The question

To ask the Secretary of State for Housing, Communities and Local Government, whether any planning applications for national significant infrastructure development consent have been delayed from the original statutory deadline since 4 July 2024.

Answered by Matthew Pennycook

There has been a total of seven planning applications delayed from the original statutory deadline since 4 July 2024.

They are as follows:

  • Cambridge Waste Water Treatment Plant;
  • Heckington Fen Solar;
  • Hinckley National Rail Freight Interchange;
  • Luton Airport;
  • Lower Thames Crossing;
  • North Lincolnshire Green Energy Park; and
  • West Burton Solar.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim