National Grid

Asked by James CartlidgeConservativeDepartment for Energy Security and Net ZeroTabled Answered 29 November 2024UIN 16211

The question

To ask the Secretary of State for Energy Security and Net Zero, if he will make an estimate of the cost of building (a) the Western link and (b) all current and future stages of the Eastern Link if that route was primarily overland via pylons instead of offshore cabling.

Answered by Michael Shanks

Ofgem reviews proposed project costs and ensures that network companies spend efficiently. Electricity network reinforcements are only approved where they are in the interests of consumers and help reduce system costs.

Ofgem identified a net lifetime benefit for Western Link, due to lower project and constraint costs compared to alternatives. [1] The system operator set out the project need case in 2007.

Ofgem’s analysis [2]of Eastern Green Link 1 and 2, noted that onshore reinforcements would not achieve required delivery dates resulting in increased constraint costs.

[1] https://www.ofgem.gov.uk/consultation/transmission-investment-incentives-consultation-minded-position-western-high-voltage-direct-current-hvdc-link-western-bootstrap

[2]https://www.ofgem.gov.uk/consultation/eastern-hvdc-consultation-projects-initial-needs-case-and-initial-thinking-its-suitability-competition

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim