Network Rail

Asked by Laurence TurnerLabourDepartment for TransportTabled Answered 29 November 2024UIN 16372

The question

To ask the Secretary of State for Transport, with reference to page 8 of the Network Rail publication entitled 2022 Delivery Plan Update: North West and Central, published in May 2022, what was the outturn proportion of investment milestones that were missed in that region in (a) 2022-23 and (b) 2023-24; and what were the investment milestones that were missed in that region by each item in (i) 2022-23 and (ii) 2023-24.

Answered by Simon Lightwood

There were no milestones missed for (a) Financial Year 22/23. For (b) 23/24, the outturn as a percentage for missed milestones was 2%. The two missed milestones were:

· Worcester Shrub Hill Canopies, which was the delivery of the scope of buildings work

The programme was delayed by site access and safety issues, including visibility of signals and the scope of works was increased as the assets were in a worse condition than anticipated.

· The Three Arch bridge between Cuddington and Delamere stations, which was a renewal of a 3-span bridge.

Further inspection of the asset showed that it was not in as bad condition as expected and it was deemed an inefficient use of public funds to progress with the work.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →