Sizewell C Power Station

Asked by Andrew BowieConservativeDepartment for Energy Security and Net ZeroTabled Answered 17 December 2024UIN 18591

The question

To ask the Secretary of State for Energy Security and Net Zero, what steps his Department is taking to construct grid connections for Sizewell C.

Answered by Michael Shanks

The policy position outlined in the National Energy System Operator (“NESO”) open letter [https://www.neso.energy/document/349496/download] (published 10th December 2024) indicates that, given Sizewell C received planning consent in July 2022, the existing arrangements for Sizewell C grid connection should be eligible to be grandfathered, subject to NESO’s proposals for reforming the connections process being approved by Ofgem and taking effect.

National Grid Electricity Transmission has also confirmed that Sizewell C will retain the same enabling works identified in previous connection agreements (2007-2009).

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim