The question

To ask the Secretary of State for Energy Security and Net Zero, what steps his Department is taking to construct grid connections for North Lincolnshire Energy Park.

Answered by Michael Shanks

Northern Powergrid (NPg) and National Grid Electricity Transmission are responsible for the construction of the connections. I understand from NPg that the connection infrastructure is expected to be completed in 2027. Energisation dates will be specific to each customer in the energy park.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim