To ask the Secretary of State for Energy Security and Net Zero, whether his Department is taking steps to extend the operation of existing nuclear power plants beyond 2030.

Answered by Michael Shanks

EDF have recently announced extensions to the Advance Gas-cooled Reactor nuclear power stations. Heysham 1 and Hartlepool are now expected to operate until March 2027 and Heysham 2 and Torness are now expected to operate until March 2030. Sizewell B is currently scheduled to operate until 2035.

The Government is not involved in the decision-making process to extend the operating lifetime of nuclear power stations. The recent decisions to extend the Advance Gas-cooled Reactor fleet have been taken by EDF based on safety and commercial assessments.

As set out in our Clean Power 2030 Action Plan, nuclear will continue to play a key role in the energy system out to 2030 and beyond with the operation of Sizewell B and delivery of Hinkley Point C.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim