Wind Power: Lytham St Annes

Asked by Mr Andrew SnowdenConservativeDepartment for Energy Security and Net ZeroTabled Answered 29 January 2025UIN 25386

The question

To ask the Secretary of State for Energy Security and Net Zero, whether proposals to temporarily close parts of St Anne’s beach to lay cables to connect the Morgan and Morecambe windfarm to its substations includes provisions to compensate affected business owners.

Answered by Michael Shanks

All relevant information on the Morgan and Morecambe transmission assets can be found on the appropriate project page of the Planning Inspectorate website. The developers set out their proposals for a contingency fund to address temporary business disruptions caused by necessary construction works in their Development Consent Order Application documents.[1]

[1] https://infrastructure.planninginspectorate.gov.uk/wp-content/ipc/uploads/projects/EN020032/EN020032-000632-D1.1_MMTA_Annex%201%20Morgan%20Offshore%20Wind%20Limited%20Property%20Cost%20Estimate.pdf

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →