STEP Programme: Burton

Asked by Andrew BowieConservativeDepartment for Energy Security and Net ZeroTabled Answered 30 January 2025UIN 25716

The question

To ask the Secretary of State for Energy Security and Net Zero, what recent progress his Department has made on implementing the Spherical Tokamak for Energy Production (STEP) prototype fusion power plant at West Burton.

Answered by Kerry McCarthy

On 16 January 2025, the Government announced £410m of investment to accelerate development of fusion energy. This is to fund UK fusion programmes in 2025-2026, including STEP.

On the same day, UKIFS – the UKAEA subsidiary that will deliver STEP – announced the shortlist of construction and engineering partners selected for the next stage of the STEP procurement process. Contracts for successful bidders are set to be awarded by early 2026. By involving private industry early, the programme will maximise development of the fusion supply chain and adjacent sectors. Other progress in recent months includes the formal transfer of the programme’s leadership to the delivery body, UKIFS.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim