Coryton Energy Park: Fire Prevention
The question
To ask the Secretary of State for Energy Security and Net Zero, what steps he plans to take to help reduce fire risk at Coryton Energy Park.
Answered by Michael Shanks
Planning applications for battery storage are determined by the local planning authority under the Town and Country Planning Act regime. The operation of this regime and the decisions made under it are the responsibility of the Ministry of Housing, Communities and Local Government. The Health and Safety Executive regulates grid-scale batteries within a robust framework which requires industry to act at all stages of the battery’s deployment to ensure safety. Of particular relevance to fire safety, the Dangerous Substances and Explosive Atmospheres Regulations (2002) set out requirements to protect workers and others from fire risks.
Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →