Type 26 Frigates: Procurement

Asked by Mr Mark FrancoisConservativeMinistry of DefenceTabled Answered 4 March 2025UIN 33407

The question

To ask the Secretary of State for Defence, how many Type 26 frigates the his Department plans to order from BAE Systems; and whether this number is still subject to the outcome of the Strategic Defence Review.

Answered by Maria Eagle

The Strategic Defence Review will consider all Defence capability requirements in the context of current and future threats.

The T26 programme remains on track to meet all user requirements and deliver eight world-class anti-submarine warfare frigates. All ships are expected to enter service between 2028 and 2035.

HMS Venturer will be the first in Class of the Type 31 and is scheduled to be In service and ready for operations by the end of the decade. All five Type 31 ships are planned to be in service by the early 2030s.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim