Asked by Sir John HayesConservativeDepartment for Energy Security and Net ZeroTabled Answered 18 March 2025UIN 36580

The question

To ask the Secretary of State for Energy Security and Net Zero, if (a) his Department and (b) Ofgem will make an estimate of the cost of the construction of (i) National Grid's proposed Grimsby to Walpole pylon scheme and (ii) alternative schemes to transmitting electricity on the route including underground cabling.

Answered by Michael Shanks

The Department cannot comment on specific projects which will come before the Secretary of State for a final planning decision. It is the responsibility of the developers of electricity network projects – in this case National Grid Electricity Transmission - to propose a route and obtain planning permission for that route. Ofgem reviews proposed project costs and ensures that network companies spend efficiently, protecting consumers from unduly high costs.

In general, undergrounding costs an estimated 5 to 10 times more than overhead lines. The cost of building this infrastructure is borne by electricity bill payers so it is key we keep costs down.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim