High Speed 2 Line

Asked by Seamus LoganScottish National PartyDepartment for TransportTabled Answered 28 April 2025UIN 44833

The question

To ask the Secretary of State for Transport, what her Department's original budget for HS2 Phase 2 was; how much her Department has spent since that project started; and what the estimated final cost is in (a) real and (b) current terms.

Answered by Lilian Greenwood

The original funding envelopes (in 2015 prices) for Phase 2a was £3.72bn and £24.8bn for Phase 2b. Spend on the HS2 project can be found in the latest Parliamentary Report here , which is updated and published at regular intervals. The project currently reports estimated final costs in 2019 prices.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim