Hinkley Point C Power Station

Asked by Seamus LoganScottish National PartyDepartment for Energy Security and Net ZeroTabled Answered 28 April 2025UIN 44834

The question

To ask the Secretary of State for Energy Security and Net Zero, what his Department's original budget for the construction of Hinkley Point C was; how much his Department has spent since that project started; and what the estimated final cost is in (a) real and (b) current terms.

Answered by Michael Shanks

Hinkley Point C is not a UK Government-funded project. The financing of Hinkley Point C is the responsibility of EDF (Électricité de France) and China General Nuclear Power Corporation (CGN). The latest update from EDF on costs of Hinkley Point C can be found here (on page 29):

https://www.edf.fr/sites/groupe/files/2025-03/annual-results-edf-2024-presentation-2025-03-07.pdf

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim