Solar Power: Planning Permission

Asked by Nick TimothyConservativeDepartment for Energy Security and Net ZeroTabled Answered 28 April 2025UIN 45159

The question

To ask the Secretary of State for Energy Security and Net Zero, how many large area solar proposals going through the Nationally Significant Infrastructure Projects process are requesting planning approval to acquire freehold land.

Answered by Michael Shanks

An application for development consent can include a request for the granting of rights to compulsorily acquire or temporarily possess land to facilitate the development of the proposal.

Each application for development consent for nationally significant infrastructure projects (NSIP), including solar NSIPs, has a dedicated webpage on the Planning Inspectorate’s website which sets out its intention to acquire land or not: https://national-infrastructure-consenting.planninginspectorate.gov.uk/.

As part of the application process, a ‘Book of Reference’ is uploaded to the relevant proposal’s webpage listing the Classes of Rights which are being sought over each plot, including acquiring freehold, if applicable.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim