VerbatimParliament, as it happens

Electronic Tagging: Contracts

Asked by Bell Ribeiro-AddyLabourMinistry of JusticeTabled Answered 1 May 2025UIN 46825

The question

To ask the Secretary of State for Justice, what are the performance indicators agreed with Serco as part of the contract to provide electronic monitoring services.

Answered by Alex Davies-Jones

During the procurement of the Field and Monitoring Service contract, all suppliers were required to provide details of their vetting, staff recruitment, training and retention processes and these were assessed as part of the evaluation process. As with all of our contracts, we have robust mechanisms in place to hold Serco to account, including provisions to address under-performance. We have set out that Serco must deliver robust training that they are continually reviewing it for areas of improvement

The contract outlines the ongoing requirements Serco staff must meet in terms of pre-employment checks, additional vetting and specific national security vetting clearance.

There are 14 Key Performance Indicators within the Field and Monitoring Service contract held by Serco. Detailed information on the 14 Key Performance Indicators is available on Contracts Finders under Schedule 3 of the contract: Electronic Monitoring Field and Monitoring Service (FMS) - Contracts Finder.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →