Asked by James CartlidgeConservativeMinistry of DefenceTabled Answered 6 May 2025UIN 48140

The question

To ask the Secretary of State for Defence, pursuant to the Answer of 7 April to Question 43178 on Defence: Procurement, what expenditure is involved in the Defence Marine Services - Next Generation; and when the business case was first submitted.

Answered by Maria Eagle

The Full Business Case (FBC) was submitted to the Department’s Investment Approval Committee (IAC) members on 21 January 2025. Permission to proceed with the award of contracts was received on 9 April 2025.

The FBC authorised an Approved Budgetary Limit of £1.393 Billion over 10 years for the DMS-NG programme (including Ministry of Defence cost and risk provision).

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim