East Park Energy

Asked by Ben Obese-JectyConservativeDepartment for Energy Security and Net ZeroTabled Answered 14 May 2025UIN 50959

The question

To ask the Secretary of State for Energy Security and Net Zero, at what stage the nationally significant infrastructure project application for the East Park Energy Solar Park from Brockwell Storage and Solar is at.

Answered by Michael Shanks

The East Park Energy project is currently at the pre-application stage and is expected to be submitted to the Planning Inspectorate by September 2025: https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010141

Brockwell Storage and Solar recently consulted on their detailed plans for East Park Energy as part of a statutory consultation, which ran between 24 September and 29 October 2024: https://eastparkenergy.co.uk/our-proposals/

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →