VerbatimParliament, as it happens

Flood Control: Licensing

Asked by Jonathan DaviesLabourDepartment for Environment, Food and Rural AffairsTabled Answered 22 May 2025UIN 52957

The question

To ask the Secretary of State for Environment, Food and Rural Affairs, what the average length of time was between the Environment Agency receiving a flood risk activity permit application and starting the determination process for the approval of said permit in the latest period for which data is available.

Answered by Emma Hardy

Flood risk activity permit applications are currently being allocated for assessment a maximum of 14 weeks from receipt.

For time critical applications that pose a significant risk to people or the environment, or where required for national infrastructure projects, we prioritise the assessment of the application. Currently about 40% of applications are prioritised.

A number of initiatives are underway to reduce application processing timelines, such as additional resourcing and streamlining our regulatory approach.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim