The question

To ask the Secretary of State for Transport, whether she has had discussions with Network Rail on a timetable to install lighting on the footbridge at Slade Green Station.

Answered by Lilian Greenwood

Bexley London Borough Council approached Network Rail with a proposal to retrofit LED lighting to the underside of the footbridge handrails at Slade Green station. Network Rail has held meetings with Bexley Council representatives to discuss the proposal and has prepared and issued a Basic Asset Protection Agreement to the council.

Network Rail is working closely with Bexley Council to finalise the outstanding agreements required to move forward with the proposals and remains supportive. The timeframe for the works is influenced by several factors, including the scope of the project, track access, design reviews, and more. We anticipate being able to provide a clearer timeline once the outstanding agreements with the council have been finalised.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim