Reservoirs: Cambridgeshire

Asked by Steve BarclayConservativeDepartment for Environment, Food and Rural AffairsTabled Answered 16 June 2025UIN 54754

The question

To ask the Secretary of State for Environment, Food and Rural Affairs, what his planned timeline for for the proposed Fens Reservoir is for the (a) submission of a development consent order application to the Planning Inspectorate, (b) final decision on the development consent order application, (c) construction work to start on site, (d) construction work to finish on site, and (e) for the reservoir to be operational.

Answered by Emma Hardy

Anglian Water is responsible for the development of the Fens reservoir. Proposals will be consulted on and will follow the requirements of the National Policy Statement for Water Resources Infrastructure. A traffic and transport assessment is currently underway and further information will be shared with communities as part of the next phase of consultation this Autumn.

Anglian Water will submit the application for a Development Consent Order in 2027. The determination of the application by the Secretary of State is expected in 2028/29 and should Development Consent be granted, construction of the reservoir will start in 2029/30.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim