Project Gigabit: Lancashire
The question
To ask the Secretary of State for Science, Innovation and Technology, how much funding had been (a) allocated in total, (b) spent on and (c) forecast for the Project Gigabit contract in Lancashire on 30 May 2025.
Answered by Chris Bryant
Openreach is delivering a £149.7 million contract to bring gigabit-capable broadband to 54,300 premises in Lancashire, North Wiltshire, South Gloucestershire, West and Mid Surrey, Staffordshire, West Berkshire and Hertfordshire. This funding is allocated to all areas listed in this contract and is not explicitly allocated at a regional or constituency level.
Openreach has only recently started its build in Lancashire under this contract, so no funding has yet been paid to the supplier for its work there.