The question

To ask the Secretary of State for Energy Security and Net Zero, what the condition is of the Moyle Interconnector; and what plans he has for the development of new energy interconnectors between Great Britain and Northern Ireland.

Answered by Michael Shanks

Moyle is a point-to-point interconnector that has been in operation since 2002. It is a commercially developed interconnector and operates without government financial support.

On future interconnection between Great Britain and Northern Ireland, Ofgem gave in-principle approval in November 2024 for the proposed LirIC electricity interconnector. This project is being taken forward under the Ofgem cap and floor regulatory regime.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim