Ajax Vehicles: Procurement

Asked by Ben Obese-JectyConservativeMinistry of DefenceTabled Answered 1 September 2025UIN 69520

The question

To ask the Secretary of State for Defence, what his planned delivery timeline is for all variants of vehicles within the Armoured Cavalry Programme between (a) 21 July and 31 December 2025 and (b) 2026 and beyond.

Answered by Maria Eagle

The Armoured Cavalry Programme plans to deliver a further 55 platforms between July 2025 and December 2025. 182 platforms will be delivered by the end of 2025. A breakdown by variant is provided below.

AJAX

26

ARES

5

APOLLO

1

ATLAS

10

ATHENA

13

ARGUS

0

It is anticipated that a further 110 platforms will be delivered in 2026, with the remaining 297 platforms delivered by 2028.

To ensure alignment to the Army fielding plan and Defence priorities, the variant mix of vehicles is reviewed and agreed annually.

The programme remains on track to deliver all 589 vehicles by September 2029 as contracted.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim