Solar Power: Housing

Asked by Martin WrigleyLiberal DemocratDepartment for Energy Security and Net ZeroTabled Answered 8 September 2025UIN 73292

The question

To ask the Secretary of State for Energy Security and Net Zero, what estimate he has made of the potential impact of delays in (a) processing applications for solar panel installations and (b) issuing Distributor Network Operator reference numbers on household finances.

Answered by Michael Shanks

No estimate has been made.

Most domestic solar installations (<3.68kW) can be made under G98 regulations, whereby no application is required – the installer must merely notify the DNO within 28 days of commissioning. Households can benefit from bill savings immediately.

We are aware of some delays in customers’ receiving the Meter Point Administration Number required to sell electricity under the Smart Export Guarantee. The Government keeps this issue under review.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim