Ajax Vehicles: Procurement
The question
To ask the Secretary of State for Defence, what progress he has made in delivering the Armoured Cavalry 2025 Programme.
Answered by Luke Pollard
The Armoured Cavalry programme continues to remain on track to achieve Initial Operating Capability by December 2025.
As at 1 September 2025, 143 Ajax platforms have been accepted by the Ministry of Defence, of which 135 have been delivered to the Field Army.
The programme will deliver all 589 vehicles by September 2029 as contracted.