Asked by Ben Obese-JectyConservativeMinistry of Housing, Communities and Local GovernmentTabled Answered 19 September 2025UIN 75317

The question

To ask the Secretary of State for Housing, Communities and Local Government, with reference to the UK’s Modern Industrial Strategy, CP 1337, published on 23 June 2025, how many (a) gigafactories, (b) laboratories and (c) data centres have opted in to being designated as Nationally Significant Infrastructure Projects.

Answered by Matthew Pennycook

No gigafactories, data centres or laboratories have yet opted into the Nationally Significant Infrastructure Projects (NSIP) consenting process.

Regulations which will enable large-scale data centres to ‘opt in’ to the NSIP consenting process are intended to be laid in Parliament for approval later this year and we anticipate a number of applicants will make use of the process once they are able to do so.

Gigafactories and laboratories can already request to ‘opt in’ to the NSIP consenting regime under existing prescriptions of types of business or commercial projects in the Infrastructure Planning (Business or Commercial Projects) Regulations 2013.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim