VerbatimParliament, as it happens

Boxer Vehicles: Procurement

Asked by Mr Mark FrancoisConservativeMinistry of DefenceTabled Answered 13 October 2025UIN 77474

The question

To ask the Secretary of State for Defence, for what reason the Boxer armoured vehicle programme has been further delayed in reaching its Initial Operating Capability.

Answered by Luke Pollard

The approved Initial Operating Capability of the Mechanised Infantry (Boxer) programme is currently Q4 2025. It is under review and an update will be provided shortly.

The programme has faced some delays that have primarily resulted from global supply chain issues which are not unique to Boxer or Defence. These have, therefore, impacted industry manufacture, delivery and training timelines.

Trials have, however, progressed well; training and support work is underway, and a steady progression of vehicles are being received month on month for acceptance before being fielded to Field Army units.

Once in service, maintenance and support for the Boxer vehicle in 3rd (UK) Division will be initially led by the holding units and Royal Electrical and Mechanical Engineers maintainers along with support from Field Service Representatives from industry. Spares and support will be provisioned through our NATO Support and Procurement Agency membership in collaboration with other Boxer Nations, which provides reach back to industry for deeper maintenance if required.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim