VerbatimParliament, as it happens

Prison Accommodation: Procurement

Asked by Ben Obese-JectyConservativeMinistry of JusticeTabled Answered 20 October 2025UIN 79733

The question

To ask the Secretary of State for Justice, with reference to the data tables accompanying the National Infrastructure and Service Transformation Authority Annual Report 2024-25, published on 11 August 2025, what assessment she made of the reasons for the Infrastructure and Projects delivery confidence assessment rating of red for the 10K Additional Prison Places Estate Expansion Houseblocks and Refurbishment programme.

Answered by Jake Richards

At the time of the report, both the Houseblocks and Refurbishments Programme and Category D Expansion Programme had been impacted by ISG, a supplier of prison building contracts, entering in administration in September 2024. The loss of the building contractor meant the programmes had no guaranteed route to delivery or cost certainty until the reprocurement of those contracts concluded, meaning a red assessment was appropriate at the time.

As part of contingency plans in place, we have appointed a number of replacement constructors to take over projects that were previously with ISG. These contracts have been signed, and constructors are safely taking over sites and reviewing existing designs. Once this is complete, a programme will be developed to recommence delivery.

We are committed to delivering an additional 14,000 prison places and are on track to do so by 2031; we have already delivered c.2,500 of these since taking office.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim