Midland Main Line: Repairs and Maintenance
The question
To ask the Secretary of State for Transport, what progress her Department has made on resolving clearance issues at Marle Pit on the Midland Main Line.
Answered by Simon Lightwood
Following the decision to pause further electrification of the Midland Main Line, the department has been in discussion with Network Rail regarding their plans to conclude their current activities in a safe and controlled way. This has included a review of planned route clearance works in Sutton Bonington, Nottinghamshire. As part of this review, the works at Marle Pit bridge will be replanned when funding becomes available and electrification of the route can be re-started. While this is not expected to be within the next four years, the programme is being kept under active review as part of our longer-term pipeline of schemes.