To ask the Secretary of State for Transport, what estimate she has made of the funding required for Network Rail to undertake detailed planning for the Ely Area Capacity Enhancement Scheme.
Answered by Keir Mather
The Secretary of State updated Parliament on the 7th of July regarding which rail and road infrastructure projects will progress following the completion of the 2025 Spending Review. The Ely Area Capacity Enhancement and upgrades to Haughley Junction were not among those projects funded at this time.
The previous government had committed to a number of infrastructure projects that were unfunded, this includes the EACE and Haughley Junction schemes.