Building Digital UK: Contracts

Asked by John WhitbyLabourDepartment for Science, Innovation and TechnologyTabled Answered 18 November 2025UIN 88542

The question

To ask the Secretary of State for Science, Innovation and Technology, whether her Department has made provisions for the recovery of public funds from contractors who fail to deliver on Building Digital UK contracts.

Answered by Kanishka Narayan

Payments to suppliers for delivery under Project Gigabit contracts are made once a gigabit capable connection is available to the premises. Where a supplier fails, the supplier is required to repay any public money paid through the contracts for premises which do not reach this point.

In May 2025, Building Digital UK (BDUK) and Full Fibre mutually agreed to terminate the Project Gigabit contract for the Peak District, which included some premises in the Derbyshire Dales constituency. This contract did not reach a stage where gigabit-capable connections were being delivered and therefore there was no requirement for any funding to be repaid by the supplier.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim