Water Supply: Infrastructure

Asked by Blake StephensonConservativeDepartment for Environment, Food and Rural AffairsTabled Answered 17 November 2025UIN 89007

The question

To ask the Secretary of State for Environment, Food and Rural Affairs, if she will make an estimate of the level of (a) water and (b) sewage infrastructure investment required to maintain existing levels of capacity, in the context of the Government’s plan to build 1.5 million homes in this Parliament.

Answered by Emma Hardy

Ofwat’s Price Review 2024 (PR24) final determinations set a total expenditure allowance of £104 billion over the 2025-2030 period. This provides:

  • £60 billion of base expenditure to maintain the long-term capability of assets.
  • £1.8 billion to increase capacity at sewage treatment works to accommodate population growth over the 2025-26 to 2029-30 period.
  • £8 billion for actions associated with the Water Resource Management Plans, including the Strategic Resource Options (SROs).

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim