River Thames: Flood Control

Asked by Lincoln JoppConservativeDepartment for Environment, Food and Rural AffairsTabled Answered 18 November 2025UIN 89345

The question

To ask the Secretary of State for Environment, Food and Rural Affairs, where the River Thames Scheme is on the Environment Agency's register.

Answered by Emma Hardy

Taking the register referred to as meaning a risk register, the River Thames Scheme is managed as part of the Environment Agency’s (EA’s) capital FCRM Investment programme and is therefore captured within the wider programme-level corporate risk register, rather than as an individual project risk. FCRM Investment programme risks are overseen and managed through the Government Major Projects Portfolio (GMPP) assurance framework, ensuring consistent oversight and mitigation across all major schemes. The approach focuses on managing uncertainty and delivery risk collectively to ensure the programme remains within acceptable risk tolerance while maintaining delivery confidence and value for money. The EA’s risk management framework follows standards set out in the UK Government ‘Orange Book’.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →