Prisons: Construction

Asked by Ben Obese-JectyConservativeMinistry of JusticeTabled Answered 20 November 2025UIN 89774

The question

To ask the Secretary of State for Justice, how many new prisons have been (a) planned and (b) approved since 5 July 2024.

Answered by Jake Richards

As set out in the December 2024 10-Year Prison Capacity Strategy, we are committed to delivering an additional 14,000 prison places and aim to do so by 2031; we have already delivered c.2,600 of these since taking office.

No new prisons have been (a) planned or (b) approved since 5 July 2024.

However, since 5 July 2024, the delivery of c.1,080 places have been approved through the Small Secure Houseblocks programme at the following sites:

  • HMP Northumberland

  • HMP Lancaster Farms

  • HMP Humber

  • HMP Ranby

  • HMP Onley

  • HMP Erlestoke

We have also uplifted the Accelerated Houseblock Delivery Programme by c.125 places at HMP Wayland.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim