VerbatimParliament, as it happens

Network Rail: Clocks and Watches

Asked by Mr Richard HoldenConservativeDepartment for TransportTabled Answered 26 November 2025UIN 91467

The question

To ask the Secretary of State for Transport, how much expenditure has been incurred for the new Network Rail clock design to date; and what is the budget for the programme as a whole.

Answered by Keir Mather

Network Rail’s new clock design was the subject of an international competition launched in April 2023 under the previous Government. The winning team received £35,000 for the purchase of the Intellectual Property rights to the design, and runners up shared an additional £35,000. Installation of the one-off clock at London Bridge cost Network Rail £120,000 and is the largest circular digital screen on the UK rail network – sized to provide clear visibility for 200,000 passengers passing it each day.

The rollout of the clock to other stations has been delivered as part of a wider programme of accessibility and inclusivity upgrades to customer information systems, costing Network Rail £330,000. Network Rail do not have a separated estimate of cost for the specific clock element of this.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim