To ask the Secretary of State for Transport, what (a) land and (b) property was acquired for the construction of the HS2 Phase 2b Eastern Leg route from Birmingham to Leeds is (i) still held, (ii) sale pending and (iii) sold.

Answered by Simon Lightwood

562 properties have been acquired for HS2 on the former Phase 2b East route between Birmingham and Leeds. These are 20 agricultural units; including land where there are no dwellings, 5 commercial properties and 537 residential properties.

In 2022, 6 of these properties on the former Phase 2b East route were sold as part of a pilot disposal project.

In July, safeguarding was removed along the majority of the former HS2 Phase 2b Eastern Leg. We are now initiating a programme to dispose of properties on the former Eastern Leg that are no longer required. We expect disposals on the open market to begin in 2026. Before then, former owners whose property was acquired under statutory blight will have the opportunity to reacquire their former property at the current market value.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim