Flood Control: Expenditure
The question
To ask the Secretary of State for Environment, Food and Rural Affairs, further to her answer to Q92990 if she can break down the annual expenditure and the total £4.2 billion into capital and revenue.
Answered by Emma Hardy
As part of the Government’s Plan for Change, we are investing £4.2 billion over three years (2026/27 to 2028/29) to construct new flood and coastal erosion schemes and maintain and repair existing defences across the country.
This is £1.4 billion on average each year – a 5% increase on the current average of £1.33 billion over 2024/25 and 2025/26.
Further details will be published in due course, including the split between capital and revenue funding.