Wind Power: Irish Sea
The question
To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of the ability of vulnerable groups to participate in consultations on the Morgan and Morecambe offshore windfarm cabling route.
Answered by Michael Shanks
The applicant must carry out a consultation in compliance with the Planning Act 2008 as part of the pre-application procedure for any nationally significant infrastructure project such as this. Applicants, the Planning Inspectorate and the Secretary of State must also ensure compliance with the relevant secondary legislation made under the Planning Act 2008, and have regard to the requirements in the Equality Act 2010 (such as Section 149 ‘Public sector equality duty’), providing accessible engagement opportunities for potentially affected parties, including those in vulnerable groups.