River Thames: Flood Control

Asked by Dr Ben SpencerConservativeDepartment for Environment, Food and Rural AffairsTabled Answered 9 February 2026UIN 110069

The question

To ask the Secretary of State for Environment, Food and Rural Affairs, what progress her Department has made on the River Thames Scheme; what her planned timetable is for that scheme; and what the (a) current and (b) projected expenditure is for that scheme, in the context of the project’s mid-project review.

Answered by Emma Hardy

Significant progress has been made in preparing for The River Thames Scheme to undergo Statutory Consultation to inform the application of a Development Consent Order (DCO).

The mid-project review, initiated by Project Sponsors: The Environment Agency (EA) and Surrey County Council, is ensuring the scheme design is optimised before finalising the DCO.

In addition, the Sponsors commissioned the National Infrastructure and Service Transformation Authority (NISTA) to independently assess the readiness of the project and sponsoring organisations to deliver the project. The cost of the development work up to this point has been £104 million.

The EA will be bringing forward an updated business case this Summer, which will set out the revised timetable to submit the DCO, an updated cost assessment, and any revised arrangement for delivery of the scheme.

Subject to approval of this business case, the next stage in progressing the project is to secure the DCO.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim