VerbatimParliament, as it happens

Railways: Wales

Asked by Ann DaviesPlaid CymruDepartment for TransportTabled Answered 24 February 2026UIN 113206

The question

To ask the Secretary of State for Transport, in pursuant to the answer to question 109355, of the £2.5 billion forecast to be spent between 2024 - 2029, how much of this is OMR spending on the Wales Route and how much is other additional costs for the Wales Route.

Answered by Keir Mather

£1.9 billion OMR funding has been allocated to the Wales and Borders route for the five years between 2024 and 2029. The remaining funding is expected to be spent on other costs associated with the route as well as infrastructure enhancements to invest in the areas that matter most to passengers and freight users.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.