Electric Cables

Asked by Ann DaviesPlaid CymruDepartment for Energy Security and Net ZeroTabled Answered 9 March 2026UIN 118014

The question

To ask the Secretary of State for Energy Security and Net Zero, with reference to the National Policy Statement for Electricity Networks Infrastructure (EN-5), on what evidential basis his Department has determined that overhead lines should be the strong starting presumption for electricity network developments in general.

Answered by Michael Shanks

The starting presumption for electricity network developments set out in EN-5 is based on several factors including cost, environmental and technical points.

Overhead lines are quicker and easier to construct, cause less environmental disturbance during construction, are easier to maintain and repair, and are simpler to connect to existing circuits.

Evidence indicates that overhead lines are significantly cheaper than undergrounding, with the Institution of Engineering and Technology (April 2025) estimating undergrounding costs around four and a half times more.

As these costs are ultimately borne by electricity bill payers, overhead lines remain the Government’s starting presumption.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim