To ask the Secretary of State for Energy Security and Net Zero, what consideration his Department has given of the potential merits of increasing the electricity export limit of 3.68 kW for domestic renewable energy systems without prior approval from the Distribution Network Operator.
Answered by Michael Shanks
The Department recognises that the export threshold may restrict some households seeking to maximise the benefits of generation. Ofgem, as part of its Connections End‑to‑End Review, has proposed to ask DNOs to review the threshold with the view to increase it (page 83 - https://www.ofgem.gov.uk/sites/default/files/2025-12/connections-end-to-end-review-next-steps-final.pdf). The Department is engaging closely with Ofgem, network companies and other stakeholders as this work progresses.