M6: Repairs and Maintenance
The question
To ask the Secretary of State for Transport, what the total duration in hours was of (a) partial and (b) full closures as a result of the M6 Lune Gorge project.
Answered by Simon Lightwood
Between 1 September 2025 and 14 April 2026, all recorded closures associated with preparatory works were partial closures only, affecting a single northbound or southbound carriageway, or lane closures. There were 18 overnight carriageway closures, each operating within a standard nine hour window (8pm – 5am), giving up to 162 hours of partial closures. In addition, lane closures from January 2026 total up to 270 hours. There were no full closures affecting both directions simultaneously during this period.