East Suffolk Line: Standards

Asked by Jenny Riddell-CarpenterLabourDepartment for TransportTabled Answered 22 April 2026UIN 126442

The question

To ask the Secretary of State for Transport, whether her Department has made an assessment of the potential impact of freight operations associated with Sizewell C on (a) passenger capacity, (b) journey times and (c) service frequency on the East Suffolk Line in the long-term.

Answered by Keir Mather

The train operator Greater Anglia is aware that freight traffic in relation to the constructions of Sizewell C is likely to increase in the future. Network Rail will continue to work closely with operators to assess how best to accommodate the additional freight services while protecting current passenger train service levels on the route.

There has been a specific workstream dedicated to operational readiness including timetabling and capacity and Network Rail identified capacity within the timetable to enable four additional Sizewell freight trains to operate some time ago.

Separately, Sizewell has also commissioned Network Rail to do a feasibility study on what would need to be true to improve passenger services on the East Suffolk branch line to support the local area.

The Rail Minister recently met with Jenny Riddell-Carpenter on 24 March to discuss this matter. Greater Anglia has recently confirmed that from the May 2026 timetable change, additional later trains will operate from Lowestoft to Beccles and from Beccles to Lowestoft on Mondays to Saturdays.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim