The question

To ask the Secretary of State for Energy Security and Net Zero, whether any review was undertaken of the mitigation package secured through the Sizewell C Deed of Obligation following the increase in the project’s estimated cost.

Answered by Michael Shanks

The Deed of Obligation was agreed between Suffolk Council, East Suffolk Council, and NNB Generating Company (SZC) Limited in October 2021. It sets out mitigation measures to reduce the impact of the development and operation of Sizewell C within each Councils boundary and is reflected in Requirements within the Development Consent Order. We are not aware of any review of the mitigation package in the light of increased project costs. Any application to change the Orders Requirements would need to be approved by the Secretary of State.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim