Asked by Rebecca SmithConservativeDepartment for TransportTabled Answered 20 May 2026UIN 918

The question

To ask the Secretary of State for Transport, with reference to the Answer of 24 March 2026 to Question 118920, whether she has plans to undertake a BCR assessment for the dualling of single sections of the Clitheroe to Manchester Victoria line.

Answered by Keir Mather

The most recent appraisal was undertaken in 2014 as part of the Blackburn to Manchester Rail Scheme, which assessed options to double the single-track sections between Blackburn and Bolton.

The preferred option was to extend the Darwen passing loop, which presented a core BCR of 1.67. The £13.8 million scheme was funded by Blackburn & Darwen Council and the Local Growth Fund. It was delivered by Network Rail in 2015 and the half hourly rail service between Blackburn and Manchester Victoria commenced in December 2017.

The Department has no plans to undertake further economic analysis or development work on this corridor, but would welcome discussions with Lancashire County Combined Authority, should they wish to prioritise any such analysis locally.

Verbatim has judged this answer against the question that was actually asked — answered, partly answered, or evaded. Sign in to see the verdict →

Open this question in Verbatim →

Every written question, searchable

155,000 questions tabled since the election, with the answer each department gave — and the ones still unanswered, with the clock running. Free to search.

Search written questions →Read on Verbatim